P
age 2 of 5
September 2021
Dry Wells shall be setback a minimum of five feet from water and sewer house connections
and a minimum of three feet from all other utilities unless a greater setback is required by the
utility company. All utilities (for instance water, sewer, gas and electric) must be shown on the
plan so setbacks can be verified.
S
etback requirements apply to items on adjacent properties also. Plans must show structures,
wells, septic, etc. on adjacent properties so required setbacks to off-site improvements can be
verified.
D
ry Wells and outfall pipes may not be placed within any existing or proposed easements
including P.U.E.’s., P.I.E.’s, and other easements adjacent to the public Right-of-Way (ROW).
However, where no adjacent easement is present Dry Wells may be placed directly next to, but
out of, the ROW with no setback. Refer to the DPS Dry Well for Roof Runoff Detail (Dry Well
Detail) for other minimum setback and location requirements. Setbacks to features on adjacent
properties (i.e. structures, wells, septic systems) must also be considered and compliance must
be illustrated on the plan.
W
hile it is preferable to locate Dry Wells down grade of building foundations, it is not a
requirement in all cases. When Dry Wells are upgrade of buildings the designer may choose
to include additional measures in the Dry Well design to discourage lateral flow to foundations.
These measures, such as impermeable liners, must be shown on the plan and a section must
be provided. Impermeable liners must never be placed at the bottom of a Dry Well.
Dry Wells can be an irregular shape but must be buildable using standard equipment and
customary construction practices. They shall not be narrower than two feet at any point or
incorporate any angles less than 45 degrees at any corners.
C. Design Criteria
1. S
izing
ESD vo
lume (ESDv) credit and the associated dry well sizing are directly related to the amount
of roof draining to a Dry Well. The total roof area permitted to drain to any individual Dry Well
is 1,000 sq.ft.
B
ecause of the 1,000 sq.ft. limitation and the relationship between roof area and Dry Well size,
it is essential that the designer use the actual roof square footage in all calculations. Each roof
segment’s flow to a gutter and to a downspout must be feasible. Finally, to ensure the correct
roof segments drain to the specific Dry Well sized to treat them, the design must include the
layout, material, and size of the solid pipe system that collects and conveys runoff from the
downspouts to the Dry Well.
O
nce the total roof area to a Dry Well is established and regardless of the site’s Target P
E
, the
P
E
used to compute the minimum and maximum ESDv is established as 1” and 2.6”
respectively. Volume credit is only given for the actual roof drainage area and P
E
achieved.
Oversizing of Dry Wells beyond the maximum ESDv is not acceptable. When a P
E
of 2.6” is
used to determine a maximum ESDv, and a Dry Well is designed accordingly, all of the ESDv
can be credited towards meeting the project’s overall requirement. This is one acceptable
method that can be used where necessary to meet the treatment requirements for areas that
do not drain to a Dry Well, such as sidewalks, areaways and decks. Note that vehicular areas
should be treated directly wherever practicable to do so, and compensation should only be
used when needed.